Yingqi Tan | Morningstar
Data centers were two-thirds of Goodman’s (ASX.GMG) $14.5 billion development pipeline at the end of March 2026, and the group remains committed to expanding it to $18 billion by June 2026. Management also reiterated its fiscal 2026 operating earnings growth target of at least 9%.
Why it matters: Between now and the end of June, Goodman wants to break ground on $3.5 billion worth of data center projects, so a lot needs to be done, and quickly. But our bigger concern with the firm’s March-quarter update is not the pace of commencements but the lack of clarity on leasing.
The bottom line: We maintain our fair value estimate of $29 per security for narrow-moat Goodman, with our forecasts unchanged.
Between the lines: Goodman is currently in negotiations with multiple prospective customers. At this stage, we don’t believe the absence of customer commitments reflects the undesirability of its data centers. We think Goodman should be able to lease them closer to completion.
Goodman operates an own-develop-manage business model. A typical cycle starts from acquiring a site and developing it. Completed projects are either sold or retained in one of Goodman’s funds or partnerships. Goodman typically retains minority stakes in the investment vehicles and continues to manage the sites after completion.
The group’s development-led strategy fuels growth of its asset base. As of December 2025, Goodman’s total assets under management reached AUD 87 billion, tripling the asset base of 10 years ago. Its development pipeline has also experienced significant expansion, growing to $14 billion by December 2025, compared with fiscal 2014’s $3 billion. With a large development pipeline and an active development strategy, we expect AUM to enjoy mid-single-digit percentage growth over the medium term, and the management segment to contribute almost 40% of the group’s midcycle operating earnings.
The pivot toward larger-scale, higher-value projects not only expands pipeline size but also increases project lead time. Today, an average development project takes about 25 months to complete, up from 17 months in 2020. This reflects a higher percentage of data center projects, an area of focus for Goodman in the short to medium term.
Despite larger developments, capital management has remained prudent. Most development projects have capital partners involved, with high tenancy precommitment and long leases secured. The company has been rotating properties into its funds or disposing of its assets to external third parties. By doing so, Goodman is redeploying capital to new opportunities and maintaining low leverage on its own balance sheet.
Goodman prefers urban infill locations in core gateway cities, and this adds to the appeal of its portfolio. These locations—typically in established and densely populated neighborhoods and close to end-consumer markets—are supply-constrained. Good locations, combined with structural tailwinds like e-commerce and cloud technology booms, are likely to underpin solid rent growth in the medium term.
All prices and analysis at 29 May 2026. This information has been prepared by Morningstar Australasia Pty Limited (“Morningstar”) ABN: 95 090 665 544 AFSL: 240 892.). Morningstar’s full research reports are the source of any Morningstar Ratings. The content is distributed by WealthHub Securities Limited (WSL) (ABN 83 089 718 249)(AFSL No. 230704). WSL is a Market Participant under the ASIC Market Integrity Rules and a wholly owned subsidiary of National Australia Bank Limited (ABN 12 004 044 937)(AFSL No. 230686) (NAB). NAB doesn’t guarantee its subsidiaries’ obligations or performance, or the products or services its subsidiaries offer. This material is intended to provide general advice only. It has been prepared without having regard to or taking into account any particular investor’s objectives, financial situation and/or needs. All investors should therefore consider the appropriateness of the advice, in light of their own objectives, financial situation and/or needs, before acting on the advice. Past performance is not a reliable indicator of future performance. Any comments, suggestions or views presented do not reflect the views of WSL and/or NAB. Subject to any terms implied by law and which cannot be excluded, neither WSL nor NAB shall be liable for any errors, omissions, defects or misrepresentations in the information or general advice including any third party sourced data (including by reasons of negligence, negligent misstatement or otherwise) or for any loss or damage (whether direct or indirect) suffered by persons who use or rely on the general advice or information. If any law prohibits the exclusion of such liability, WSL and NAB limit its liability to the re-supply of the information, provided that such limitation is permitted by law and is fair and reasonable. For more information, please click here.